Reconstruction of Ura Vajgurore Road – Pashalli Bistrovice
The works for the Reconstruction of the Road Ura Vajgurore – Bistrovice Pashalli started on 04/2013 and ended on 08/2016 a project by the Albanian Development Fund with a limit fund of 427,339,314 ALL
Some other technical data during the project have been made more than 36,750 m3 Excavation and transportation, 40,917 m3 Fixing with gravel materials, 21,730 m3 Road layer, 4,899 m3 Concrete works, 13 tons Steel works, 7,236 tons Asphalt Base Layer, 4,104 tons Bonding Asphalt