Reconstruction of Muçaj village road, Vora municipality
The cReconstruction of Muçaj village road started on 05/2006 and was completed on 09/2006 by the Vora municipality project with a limit fund of 22,763,936 ALL
Some other technical data during the project were made more than 3,240 m3 Excavation and transport, 9,000m3 Fixing with gravel material, 570 tons Asphalt layer