Reconstructing of National road – Dajc
Reconstruction of the national road – Dajc started on 01/2013 and ended on 01/2014 project developed by the Albanian Development Fund with a limit fund of 203,335,577 ALL
Some other technical data during the project have been made more than 27,640 m3 Excavation and transportation, 2,091 m3 Filling with gravel material, 23,800 m3 Road layers, 4,367 m3 Concrete work, 76,860 tons Steel works, 2,802 tons Bonding Asphalt laye, 4,722 tons Asphalt coating layer, 10,336,340 ALL Electrical Works