Construction of the Shkodra Ring Road
The Construction of the Shkodra Ring Road started on 08/2006 and was completed on 12/2007 by the DPSHTRR project with a limit fund of 376,515,913 ALL
Some other technical data during the project were made more than 50,030 m3 Excavation and transport, 30,035 m3 Fixing with gravel material, 3,898 tons Asphalt layer