Construction of Milot Fushe Kruja road – Lot 6
The Construction of Milot Fushe Kruja road – Lot 6 started on 2009 and was completed on 2010 by the DPSHTRR project with a limit fund of 585,293,268 ALL
Some other technical data during the project were made more than 77,660 m3 Excavation and transport, 234,340 m3 Fixing with gravel material, 11,191 tons Asphalt layer